Hi,
We have jobs that we want to limit their time either sitting and waiting
or running to certain number of hours. In addition, we want these jobs
to reschedule on error - essentially, start the job at X time, keep
trying to run but after Y hours end no matter what. I've found that if
you use reschedule on error and max run sched time, that the latter will
use the latest scheduled time as opposed to when the job initially was
scheduled. The database schedule time seems to stay the originally
scheduled time since it's really the same job as far as that is
concerned. This seems to all make sense but doesn't accomplish what we
want to do. I was wondering if I'm missing existing options or will
need to extend Bacula with a new Max Run Init Sched Time option which
will use that initial scheduled time when determining if the job should
be ended.
thanks,
--tom
------------------------------------------------------------------------------
Everyone hates slow websites. So do we.
Make your web apps faster with AppDynamics
Download AppDynamics Lite for free today:
http://p.sf.net/sfu/appdyn_d2d_feb
_______________________________________________
Bacula-users mailing list
Bacula-users AT lists.sourceforge DOT net
https://lists.sourceforge.net/lists/listinfo/bacula-users
|